The planning permit was approved on 16th of August 2013 and settlement took place
on 4th of September 2013.
The VMAA executive approved some funding on 10th of October and Road work
started on 16th of October 2013.
Certificate of Occupancy was issued 12 February 2015.
Official Opening 8 March 2015

13.7.14

Lining Walls

Thursday and Saturday saw a bunch of blokes hoisting plasterboard and slopping gooey blue glue, whacking nails, pushing and shoving  and a little cursing, (more than a little actually) to get the toilets and store room lined.

 NO, he hasn't been naughty, he's covering up the joins.

Not very pretty now.




Proceeding apace.