The planning permit was approved on 16th of August 2013 and settlement took place
on 4th of September 2013.
The VMAA executive approved some funding on 10th of October and Road work
started on 16th of October 2013.
Certificate of Occupancy was issued 12 February 2015.
Official Opening 8 March 2015
on 4th of September 2013.
The VMAA executive approved some funding on 10th of October and Road work
started on 16th of October 2013.
Certificate of Occupancy was issued 12 February 2015.
Official Opening 8 March 2015
27.12.14
Update
I haven't been around for a while, so it's catch up time.
Looks like we have a beaut big watering device.
The open shelter is looking very good.
Good for those hot summer days to come.
Removeable posts separating pits from parking.