About

The planning permit was approved on 16th of August 2013 and settlement took place
on 4th of September 2013.
The VMAA executive approved some funding on 10th of October and Road work
started on 16th of October 2013.
Certificate of Occupancy was issued 12 February 2015.
Official Opening 8 March 2015

24.2.14

Weekend work


February 22 & 23 saw a lot of members at the field to lay the pipe work for irrigation of the East-West runway.
First, a pipe from the dam up to the holding dam, then to the runway with 90mm pipe for the sprinkler system.





















 Lunch was provided, though most of us put some dollars in to defray the cost


 Daryl brought out his caravan and cooked up a storm.
 Weather was kind to us, not too hot.







 A wonderful effort by all who attended.