The planning permit was approved on 16th of August 2013 and settlement took place
on 4th of September 2013.
The VMAA executive approved some funding on 10th of October and Road work
started on 16th of October 2013.
Certificate of Occupancy was issued 12 February 2015.
Official Opening 8 March 2015

20.9.14

Late September

Pump is now housed
Back from my holiday, I am most impressed with the progress made during my absence.

Covered walkway.
 Battery charging station is under construction
 Interior wall is clad and the storeroom is storing stuff.
 The electrical control centre has a lot more wire connected.
 The 'Coates Hire' shed has a beaut new window facing the action.

 'Pilots boxes' are in place
 Runway mat looks well bedded in.
 Runway is growing grass.
 Bore water header tank is installed and plumbed.


















Pressure water pumps readied for operation.



(It seems I don't need to be there cracking a whip to get stuff done ;-)